Fairlie-Poplar Streetscape Project Update
January 25,2011
Delays due to unforeseen encroaching basements, utility relocations, driveway coordination and weather conditions have both delayed and necessitated re-sequencing of the project. Despite these minor delays the project continues to progress as the contractor works diligently to make up for lost time. However, the contractor will not meet the scheduled completion date of early February. The Atlanta Downtown Improvement District is currently considering the approval of a time extension for the contractor the details of which are to be determined. For questions or concerns, contact Carly Nassar at (404) 658-5915 or cnassar@atlantadowntown.com.